Aquatherm Labor Units

This handy table will give you an estimate of the time needed to install the pipe, fittings, and other components in an Aquatherm system.

If you've seen our time trial videos, you know how fast Aquatherm is to install. This handy table will give you an estimate of the time needed to install the pipe, fittings, and other components in an Aquatherm system.

Polypropylene Pressure Piping* - Labor Units (hrs)
Nominal
Pipe Size
Per Lineal
ft of Pipe
Fusion outlet
(branch size)
Elbows,
couplings
Valves
(fusion)
Adapters,
flanges
TeeCross
½" 0.04 0.110 0.13 0.163 0.10 0.17 0.21
¾" 0.05 0.116 0.16 0.200 0.12 0.21 0.26
1" 0.08 0.138 0.18 0.225 0.14 0.23 0.29
1¼" 0.06 0.149 0.20 0.250 0.15 0.26 0.32
1½" 0.07 0.165 0.26 0.325 0.20 0.34 0.42
2" 0.09 0.193 0.30 0.375 0.23 0.39 0.48
2½" 0.09 0.220 0.33 - 0.25 0.43 0.53
3" 0.11 0.248 0.45 - 0.34 0.59 0.72
4" .14 0.303 0.55 - 0.41 0.72 0.88
6" 0.15 0.378 1.22 - 0.92 1.59 1.95
8" 0.20 - 1.54 - 1.16 2.00 2.46
10" 0.25 - 1.85 - 1.39 2.41 2.96
12" 0.25 - 2.63 - 1.97 3.42 4.21
14" 0.29 - 3.20 - 2.40 4.16 5.12
16" 0.37 - 5.11 - 3.83 6.64 8.18
18" 0.41 - 5.79 - 4.34 7.53 9.26
20" 0.48 - 7.10 - 5.33 9.23 11.36
22" 0.52 - 7.55 - 5.66 9.82 12.08
24" 0.56 - 7.92 - 5.94 10.30 12.67
*Pipe and fittings per ASTM F2389, CSA B137.11, or ISO 15874
Lineal pipe lengths include one joint per pipe section.